How to Compare Fill Prices in Builder Proposals

By · Prepared with editorial assistance

The Rotonda homesite planning guide starts with the difference between existing ground and proposed levels. That difference matters when a builder puts “fill and grade” in a proposal. I would ask what volume the base price covers and what happens if the site needs more. Without those answers, the lower price may hold only for a narrow range of quantities.

Run both prices at the same quantities

Suppose two builders price the same hypothetical homesite and drawing. Both include material, hauling, placement and compaction, and both bill extra fill by installed, compacted cubic yard. The numbers below are invented for comparison; they do not describe a Rotonda lot, a builder’s quote or local market pricing.

Illustrative fill line only; assumes no separate fees or credits
Pricing detailProposal AProposal B
Base price and included volume$6,000 for up to 100 cubic yards$6,600 for up to 140 cubic yards
Each cubic yard above the included volume$40$30
Total at 115 cubic yards$6,600$6,600
Total at 150 cubic yards$8,000$6,900

At 150 cubic yards, A bills for 50 extra yards and B for 10. A starts $600 lower and finishes $1,100 higher at that volume. I would also ask what happens at 90 cubic yards: is the base price fixed, or does unused volume earn a credit? Ask for that answer in writing before counting any savings.

Agree on what will be measured

Charlotte County’s grade and fill checklist asks for approximate fill in cubic yards and a site plan showing existing and proposed drainage elevations. That estimate is a useful reference for the scope. For billing, I would still ask whether the rate applies to loose material delivered or to compacted fill in place. A delivery ticket documents a load; it does not by itself establish the installed volume.

I would have the builder identify the dated drawing, who measures the work, what record supports any extra charge, and who approves it before the included quantity is exceeded. That gives the buyer a way to check the invoice later. It is the same principle behind comparing builder allowances on a common basis: agree on what each price buys before choosing between the totals.