Business and project decisions · November 11, 2026
A Same-Price Change Can Move the Schedule
A builder can offer a substitute at the same price and still be describing a different schedule. Before agreeing, I would ask which work can continue, which work has to wait and whether the date we care about still holds.
The Tampa residential concept includes a kitchen, pantry and butler’s pantry. The builder proposal review explains why those spaces need a clear cabinetry scope. Here I would add a timing question: if the kitchen cabinets arrive later, what happens to the work that depends on them?
Follow the cabinet delivery through to the kitchen finish
Suppose, in an invented example, a substitute kitchen cabinet package meets the same scope at the same quoted price but arrives four working days later. Assume two working days from delivery to setting the cabinets and measuring for the countertop, five more to countertop installation, and two for the remaining kitchen work and checks. Both columns use the same assumptions. These intervals are for illustration, not trade lead times or a schedule for the Tampa concept.
| Step | Original package | Same-price substitute |
|---|---|---|
| Cabinets arrive | Day 10 | Day 14 |
| Cabinets set; countertop measured | Day 12 | Day 16 |
| Countertop installed | Day 17 | Day 21 |
| Kitchen work and checks finish | Day 19 | Day 23 |
The original sequence has one working day to spare. The substitute finishes three working days beyond the target if the rest of the sequence stays the same. Working backward, the latest cabinet arrival that keeps day 20 under those assumptions is day 11. That gives the builder a specific question to take to the supplier.
Ask what protects the date
If the builder expects to hold the target, I would ask which step changes and who has confirmed it. For example, can the countertop shop accept an earlier slot after the cabinets are set, or can a separate item of finish work move earlier? Ask about any extra cost before assuming a recovery plan preserves the original price. If the revised sequence is still unconfirmed, I would leave the timing question open in the decision record.
AIA Contract Documents’ G701 instructions, reviewed November 11, 2026, illustrate the distinction by addressing the description of the change, its cost and any adjustment to contract time separately. The kitchen target above is a planning milestone. Any actual effect on the overall completion date or agreement needs its own review.
My preference is to see the price and revised sequence together. A clear proposal tells me how much a choice costs, what it changes for the next crew and whether the date still works.